Gwynt y Mor offshore wind farm

Client: Harland and Wolff

Location: North Wales

Date: 2011 -

Project

Harland and Wolff secured the project from Siemens to design and build two offshore substation platforms for the Gwynt y Mor offshore wind farm; both were positioned in September off the coast of North Wales.

To ensure the highest level of Safety in A60 and AO boundaries throughout the operating life of the substation, Harland & Wolff chose CSD Sealing System's SLIPSIL Plugs and RISE Multi-cable Transit system instead of Block style Multi Cable Transits with the approval of RWE and Siemens.

CSD's experience of working in offshore industries and the performance of their products in arduous environments, helped win this work on one of the largest offshore wind farm's in the world.

Managing Director or CSD UK, David Ripley said,
"We understand that building offshore environments require the highest levels of safety and deliver solutions that are safe, cost effective and flexible. This is a very exciting project for CSD and we are delighted to be involved with the expansion of renewable energy sources, including offshore wind, around the UK."  

CSD has enjoyed a close working partnership with Harland & Wolff and Blackbourne M&E the Electrical contractor throughout the project. Blackbourne M&E additionally sub-contracted the installation of the 200 Cable Transits to CSD on the recommendation of Harland & Wolff.

The team of highly skilled installers lead by CSD 's Peter Litchfield and in partnership with CBL worked across the two offshore substations installing over 200 Cable transits in four weeks, ensuring the tight project schedule was completed on time. Blackbourne M&E, Harland and Wolff and ultimate clients Siemens & RWE were very happy with the quality of installation.

Frank Piggott, Electrical Engineering Manager at Harland and Wolff said,
"We chose the RISE multi transit system over a Blocks type compression system to provide the highest level of fire, gas and watertight integrity. We were extremely impressed with the professionalism and helpful approach of the CSD team, throughout the project. During the installation they worked seamlessly alongside both Harland and Wolff, Siemens and Blackbourne M&E, working to a very tight schedule, ensuring installation of 200 RISE cable transits on both platforms within 4 weeks."

CSD were glad to provide additional support in this prestigious project, by skill sharing and working with the customer as an integrated partner. CSD have been able to implement standards of installation across the board, resulting in a successful deliverance of a challenging project.

CSD Sealing Systems are the UK market leaders in the supply of cable and pipe sealing systems for the marine and offshore industry, having extensive experience and knowledge of supplying offshore engineers with specialist sealing solutions for almost 20 years.

For further information please email or find product details on our RISE system here.

Gwynt y mor wind farm case study
Click here to download a pdf version 

Latest News

When it comes to fire safety there can be no shortcuts

4th July 2017

As part of CSD Sealing Systems campaign to raise awareness of fire prevention and safety within buildings and specifically wh ...

Read more

Customer testimonials

See more testimonials

...multi sleeves make packing the cable duct faster, especially in larger cable ducts or when sealing trefoil or large power cables. We will be using the RISE RAPID Duct seal on our future projects.
Gerco UK Ltd

© Copyright 2011 CSD Sealing Systems Limited

Legal Information - Terms and Conditions
Design by Boxmodel Website Designers